Project Overview

Miron was responsible for the rebuild of turbine generators #1 and #2 including complete disassembly test, bearing replacement, and turbine spindle repairs. Our crews were also responsible for the demolition of three existing chillers, three cooling towers, and one gas-fired package boiler; and also for the installation of three cooling towers and two electric chillers.

Energy Market Leader

Dan Goymerac, P.E. / Vice President, Industrial Business Development, Energy
920.969.7004
dan.goymerac@miron-construction.com

Owner:

State of Wisconsin Department of Administration

Completion:

May 2010

Architect / Engineer:

Henneman Engineering Inc.