Iowa CM at Risk Toolbox

Education Referendum Support

Benefits of CMAR

Hiring a construction manager at-risk (CMAR or CM at Risk) provides the advantage of early involvement in the project, allowing for better coordination, cost control, and input during the design phase, which can result in cost savings and schedule efficiencies. Additionally, it shifts the risk of cost overruns and delays from the owner to the construction manager, fostering a collaborative approach to problem-solving and project delivery.

Timeline & Process

Hiring Your Team’s CMAR

All information is from the requirements in Chapter 26 of the Iowa Code.

ActivityMinimum Time*Maximum Time
Advertisement: Notice to Bidders14 daysN/A
Issue Request for Qualifications (RFQ)13 days45 days
Review RFQOwner’s discretion45 days
Issue Request for Pricing (RFP)N/AN/A
Review RFPOwner’s discretionN/A

*The total time frame minimum is 8 weeks.

Get Started

Tim Verheyen

Vice President, Business Development, Cedar Rapids Office

319.249.5900
tim.verheyen@miron-construction.com

Miron Construction Co., Inc.
335 French Ct. SW
Cedar Rapids, IA 52404

"*" indicates required fields

This field is for validation purposes and should be left unchanged.