Project Overview

Phase 1 of this project included the demolition of the Hoffmaster Gym and additions to the north and east side of the facility. These additions  included construction of a new fitness center, locker rooms, administrative area, aquatic center, and child care areas, totaling 55,000 square feet.

Phase 2 will include selective demolition and remodeling in the existing gym and meeting rooms, totaling 22,000 square feet. This includes complete demolition of existing pools, the childcare area, and the fitness center. The outdoor surrounding area will be restored to green space and a park-like setting with revised parking, sidewalks, islands, and landscaping.

 

Community Market Leader

Corey Brumbaugh / Vice President, Business Development, Community
920.969.7056
corey.brumbaugh@miron-construction.com

Owner:

Oshkosh YMCA

Size:

77,000 SF

Completion:

November 2017

Architect / Engineer:

Kahler Slater Architects, Inc.