Lambeau Field work on time

Posted on Oct 10, 2012 by Packer Straight

Expansion of Lambeau Field is on budget and on time for the 2013 season. Stuart Zadra with Madison-based Hammes Co., the firm managing the project, said crews are aiming to finish in the next four to six weeks work that could be delayed by cold weather. He said major steel construction is done and concrete pouring is95 percent complete. Overall, the expansion project is 65 percent complete, Zadra said. Work will continue through winter and is expected to be finished by April. Town of Menasha-based Miron Construction is the construction manager for the project.

Sorry, this link is no longer available

Leave a Reply