Miron Construction begins work on lift station and shelter at Mary Jewel Park

Posted on Feb 15, 2018 by Construction

Miron Construction Co., Inc., in partnership with AECOM, is constructing a new lift station and park shelter for the City of Oshkosh.

The 3,858-square-foot addition in Mary Jewel Park includes a new park shelter and a lift station to aid in the pumping of wastewater to a higher elevation to be processed. Miron’s scope of work on the project includes earth retention, concrete, masonry, precast and wood framing.

The $2.9 million project began in November 2017 and is scheduled to be complete in September 2018.