Project Overview

The project additions include:

  • Multipurpose 800-seat auditorium with full orchestra pit, full fly, and lighting catwalk; lobby with restrooms; set construction and storage spaces, and dressing rooms
  • New band, choir, and music classrooms
  • Secure entry vestibule

Renovation work includes:

  • New ceilings, flooring, doors; HVAC improvements; safety, electrical, and plumbing upgrades for administrative offices, library, large group instruction, and science lab classrooms
  • Fire alarm replacement
  • Relocation of the weight/fitness room to the remodeled/expanded music area.
  • Remodel/expansion of STEM and FACE areas including woods, metals, electronics, and home economics labs into existing weight/fitness spaces

The scope also includes construction of a stand-alone building to serve existing athletic fields with restrooms, concessions, ticketing, team room, and storage.

Education Market Leader

Craig Uhlenbrauck / Vice President, Education, Education
920.969.7030
craig.uhlenbrauck@miron-construction.com

Owner:

Slinger School District

Size:

42,000 SF addition | 70,000 SF renovation | 6,500 SF new (outdoor concessions building)

Completion:

August 2018

Architect / Engineer:

Bray Associates Architects, Inc.

Additional Info: