Hiring a construction manager at-risk provides the advantage of early involvement in the project, allowing for better coordination, cost control and input during the design phase, which can result in cost savings and schedule efficiencies. Additionally, it shifts the risk of cost overruns and delays from the owner to the construction manager, fostering a collaborative approach to problem-solving and project delivery.
Below is a summary of the timeline and process for hiring your team’s CM at Risk, referenced from the requirements in Chapter 26 of the Iowa Code.
| ACTIVITY | MINIMUM TIME* | MAXIMUM TIME |
| Advertisement – notice to bidders | 14 days | N/A |
| Issue Request For Qualifications (RFQ) | 13 days | 45 days |
| Review RFQ | Owner’s discretion | 45 days |
| Issue Request for Pricing (RFP) | N/A | N/A |
| Review RFP | Owner’s discretion | N/A |
| *Total time frame minimum 8 weeks |