Hiring a construction manager at-risk provides the advantage of early involvement in the project, allowing for better coordination, cost control and input during the design phase, which can result in cost savings and schedule efficiencies. Additionally, it shifts the risk of cost overruns and delays from the owner to the construction manager, fostering a collaborative approach to problem-solving and project delivery.

Below is a summary of the timeline and process for hiring your team’s CM at Risk, referenced from the requirements in Chapter 26 of the Iowa Code.

ACTIVITYMINIMUM TIME*MAXIMUM TIME
Advertisement – notice to bidders14 daysN/A
Issue Request For Qualifications (RFQ)13 days45 days
Review RFQOwner’s discretion45 days
Issue Request for Pricing (RFP)N/AN/A
Review RFPOwner’s discretionN/A
*Total time frame minimum 8 weeks  