Project Overview

Whelan Energy Center is located six miles outside of Hastings, Nebraska. Construction for this project consisted of a new 220 MW coal-fired electric generating unit. Miron executed the Superstructures contract as part of a multiple prime project delivery method. Miron’s scope of work included:

  • Approximately 5,000 CY of suspended slabs-on-metal deck and finish slab-on-grade
  • All CMU masonry.
  • HVAC and control for control room, turbine area, boiler area, and ancillary structures.
  • Roofing and insulated metal siding for the turbine area, boiler area, AQCS, and ancillary structures.
  • Miscellaneous foundation installations.
  • Furnish and installation of miscellaneous steel.
  • Fireproofing.
  • Hollow metal and overhead doors and hardware.
  • Interior build-outs throughout the plant (i.e., plumbing, metal studs/drywall, shaft wall, finishes, specialties).
  • Installation of Owner-furnished auxiliary hoists and cranes.

Energy Market Leader

Dan Goymerac, P.E. / Vice President, Industrial Business Development, Energy
920.969.7004
dan.goymerac@miron-construction.com

Owner:

Public Power Generation Agency

Completion:

August 2010

Architect / Engineer:

Black & Veatch