Project Overview

Miron was responsible for disassembly of #3 and #5 paper machines at the former P.H. Glatfelter Neenah mill site. This work included match marking and disassembly of #3 PM (26 dryer cans) and #5 PM (52 dryer cans). All equipment including headboxes, wire/felt sections, fan pumps, two bridge cranes, and other miscellaneous machine equipment in the mill was packaged and sent to India for re-assembly.

Pulp & Paper Market Leader

Dan Goymerac, P.E. / Vice President, Industrial Business Development, Pulp & Paper
920.969.7004
dan.goymerac@miron-construction.com

Owner:

P.H. Glatfelter

Completion:

June 2007